TO: Honorable Mayor and Members of the City Council
FROM: Robin Kampmann, City Engineer
SUBJECT:
title
Adopt a List of Projects for FY 2026-27, Funded by SB1
end
RECOMMENDED COUNCIL ACTION:
recommendation
City Council adopts Resolution No. 13-2026 that establishes a list of projects for the fiscal year 2026-27 that will be partially funded by SB1: The Road Repair and Accountability Act of 2017.
body
SUMMARY:
It is estimated that the City of Red Bluff will receive $416,642 in Road Maintenance and Rehabilitation Account (RMRA) funding during Fiscal Year 2026-27 from SB1. To receive this funding, the City must adopt a list of projects proposed to receive funding from the RMRA. If approved the attached Resolution adopts the proposed project list.
PREVIOUS COUNCIL ACTION:
On June 16, 2025 the City Council adopted Resolution No. 23-2025, adopting a list of projects that RMRA funds could be spent on in FY 2025-26.
On June 18, 2024 the City Council adopted Resolution No. 17-2024, adopting a list of projects that RMRA funds could be spent on in FY 2024-25.
On June 20, 2023 the City Council adopted Resolution No. 19-2023, adopting a list of projects that RMRA funds could be spent on in FY 2023-24.
On June 7, 2022 the City Council adopted Resolution No. 16-2022, adopting a list of projects that RMRA funds could be spent on in FY 2022-23.
On June 15, 2021 the City Council adopted Resolution No. 22-2021, adopting a list of projects that RMRA funds could be spent on in FY 2021-22.
On July 7, 2020 the City Council adopted Resolution No. 18-2020, adopting a list of projects that RMRA funds could be spent on in FY 2020-21.
On May 7, 2019 the City Council adopted Resolution No. 7-2019, adopting a list of projects that RMRA funds could be spent on in FY 2019-20.
On April 17, 2018 the City Council adopted Resolution No. 9-2018, adopting a list of projects that RMRA funds could be spent on in FY 2018-19.
DISCUSSION:
This is the tenth year in which the City is receiving SB1 funding, and continued participation will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, and increase access and mobility options for the traveling public. Funding these projects would not have been possible without SB1.
The proposed projects are:
• Baker Road Pavement Maintenance:
Completion of the rehabilitation/maintenance of Baker Road from Walnut Street to Walbridge Street, approximately 1.20 miles, with a useful life of 5-10 years.
• Oak Street Pavement Maintenance:
Rehabilitation/Maintenance of Oak Street from the UPRR to Washington Street, approximately 0.20 miles, with a useful life of 5-10 years.
CITY FISCAL IMPACT:
There would be no additional fiscal impact.
ATTACHMENTS:
None
CITY COUNCIL RESOLUTION NO. 13-2026
A RESOLUTION OF THE RED BLUFF CITY COUNCIL ESTABLISHING A LIST OF PROJECTS FUNDED BY SB1 2026/2027
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and signed into law by the Governor in April 2017 in order to address the significant multi-modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt a list of all projects proposed to receive funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1 by resolution, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City, will receive an estimated $416,642 in RMRA funding in Fiscal Year 2026-27 from SB 1; and
WHEREAS, this is the tenth year in which the City is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City has undergone a robust public process to ensure public input into our community’s transportation priorities/the project list; and
WHEREAS, the City used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the community’s priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate 1 street/road throughout the City this year and dozens of similar projects into the future; and
WHEREAS, the 2020 California Statewide Local Streets and Roads Needs Assessment found that the Tehama County streets and roads are in an “at-risk” condition and this revenue will help us increase the overall quality of our road system and over the next decade will bring our roads into a “good” condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant positive co-benefits statewide.
NOW THEREFORE, BE IT RESOLVED ON JUNE 16, 2026, BY THE CITY COUNCIL OF THE CITY OF RED BLUFF:
1. The foregoing recitals are true and correct.
2. The following list of newly proposed projects will be funded in-part or solely with 2026-27 Road Maintenance and Rehabilitation Account Revenues:
• Baker Road Pavement Maintenance:
Completion of the rehabilitation/maintenance of Baker Road from Walnut Street to Walbridge Street, approximately 1.20 miles, with a useful life of 5-10 years.
Estimated Construction Start: July 2026, Estimated Construction Completion: August 2026
• Oak Street Pavement Maintenance:
Rehabilitation/Maintenance of Oak Street from the UPRR to Washington Street, approximately 0.20 miles, with a useful life of 5-10 years.
Estimated Construction Start: July 2026, Estimated Construction Completion: August 2026
3. The following previously proposed and adopted projects may also utilize Fiscal Year 2026-27 Road Maintenance and Rehabilitation Account revenues in their delivery. With the relisting of these projects in the adopted fiscal year resolution, the City is reaffirming to the public and the State our intent to fund these projects with Road Maintenance and Rehabilitation Account revenues:
AYES:
NOES:
ABSENT OR NOT VOTING:
ATTEST: ___________________________
Mayor’s Signature
___________________________
Deputy City Clerk